What is a sprint? Length, sequence and purpose
A sprint is a fixed period in which a team completes an agreed amount of work. Length, the sequence of events, and when the format is not worth it.
A sprint is a fixed, agreed period — usually one to four weeks — in which a team completes an amount of work decided at the start. The scope stays stable for the duration; that is the actual point. The promise is not speed, it is that the plan holds.
The sequence
It opens with planning: the team pulls work out of the backlog and agrees what fits, usually based on story points and the velocity of previous sprints. It closes with a review of the result and a retrospective on how the team worked.
How long a sprint should be
Short enough that requirements do not change inside it; long enough that something finished comes out. Two weeks is the common compromise. More important than the number is that the length stays the same — otherwise there is no basis for comparison and velocity becomes meaningless.
When a sprint is not worth it
When your intake is unpredictable. A support or operations team that re-prioritises daily spends sprint planning writing a plan that no longer holds by Wednesday. Those teams do better with Kanban: steer the flow instead of filling timeboxes.
In Zuuna
Sprints are a layer above the board: you plan them out of the backlog, see the team's capacity including absences, and read the burndown at the end. The board underneath stays the same Kanban board.
FAQ
Can you add work during a sprint?
You always can; it is rarely wise. Every addition takes capacity away from the original commitment. If it happens regularly, that is a sign a fixed period does not suit the team's intake.
What happens to unfinished work at the end?
It goes back to the backlog and gets re-assessed. Simply carrying it over is common, but it hides the fact that the plan was too full.
Is a sprint the same as a deadline?
No. A deadline is a date for an outcome; a sprint is a recurring rhythm for planning and delivering. Sprints do not replace a roadmap.